Zorita nuclear power plant
The Jose Cabrera nuclear power plant (also known as Zorita) was the first nuclear power plant built in Spain, located next to the Tagus river in the municipality of Almonacid de Zorita, in the province of Guadalajara. It belonged to Union Electrica Madrileña (now Naturgy). It owes its name to the engineer Jose Cabrera Felipe, one of the first promoters of the construction of nuclear power plants in Spain. Construction began on July 6, 1965 and was completed in March 1968, the official inauguration was on December 12, 1968 by the dictator Francisco Franco. It had a Westinghouse PWR reactor with a power of 160 MW, its cooling system was mixed through cooling towers and the Zorita reservoir, on the Tagus river, it was decoupled from the electrical network on April 30, 2006, currently It is in the process of being dismantled.
NUCLEAR POWER PLANT
Workers needed 16
Profesors needed 8
Maximum electrical production 1920Mw
Road access 1
Pedestrian access 5
Loading and unloading area 2
High voltage connection 5
Low voltage connection 2
Nuclear fuel store 1t
Nuclear waste store 1t
Outdoor nuclear fuel store 23m2
Outdoor nuclear waste store 23m2
Water connections 2
Water tank capacity 150
Sewer connections 1
Sewer tank capacity 150
Cooling connections 1
Nuclear fuel consumption 0.016t
water consumption 4.8 m3
minimum water quality 65%
Factory connections 4
GROUNDWORKS
Gravel 88.5
Asphalt 95
Concrete 125
Workers 1350
BRICKS LAYING
Concrete 205
Steel 78.5
Bricks 80
Prefab panels 24.5
Workers 2170
BRICKS LAYING 1.0
Concrete 85
Steel 28.5
Bricks 60
Prefab panels 25.8
Workers 1040
STEEL LAYING
Steel 56.5
Workers 440
INTERIORS
Boards 20.5
Steel 38.5
Mechanical components 14.3
Electronic components 12.8
Workers 782
COOLING TOWERS
GROUNDWORKS
Gravel 92
Asphalt 98
Concrete 85
Workers 920
STEEL LAYING
Steel 38.8
Mechanical components 6.7
Electronic components 0.8
Workers 782
STEEL LAYING
Concrete 68
Steel 30.5
workers 948
La central nuclear Jose Cabrera (mas conocida como Zorita) fue la primera central nuclear construida en España, situada junto al rio Tajo en el termino municipal de Almonacid de Zorita, en la provincia de Guadalajara. Pertenecio a Union Electrica Madrileña (ahora Naturgy). Debe su nombre al ingeniero Jose Cabrera Felipe, uno de los primeros promotores de la construccion de centrales nucleares en España, se comenzo a construir el 6 de julio de 1965 y se finalizo en marzo de 1968, la inauguracion oficial fue el 12 de diciembre de 1968 por el dictador Francisco Franco. Tenia un reactor PWR de Westinghouse con una potencia de 160 MW, su sistema de refrigeracion era mixto a traves de torres de refrigeracion y del embalse de Zorita, en el rio Tajo, se desacoplo de la red electrica el 30 de abril de 2006, actualmente esta en proceso de desmantelamiento.
Trabajadores necesarios 16
Trabajadores formados necesarios 8
Produccion electrica maxima 1920Mw
Accesos por carretera 1
Accesos peatonales 5
Zonas de carga y descarga 2
Conexiones de alto voltaje 5
Conexiones de bajo voltaje 2
Almacen de combustible 1t
Almacen de residuos 1t
Almacen de combustible exterior 23m2
Almacen de residuos exterior 23m2
Conexiones de agua 2
Capacidad de depositos de agua 150
Conexiones de alcantarillado 1
Capacidad de depositos de alcantarillado 150
Conexiones de refrigeracion 1
Consumo de combustible nuclear 0.016t
Consumo de agua 4.8 m3
Calidad de agua minima 65%
Conexiones de fabrica 4
CENTRAL NUCLEAR
PREPARATORIOS
Grava 88.5
Asfalto 95
Hormigon 125
Dias de trabajo 1350
TENDIDO DE LADRILLO
Hormigon 205
Acero 78.5
Ladrillos 80
Paneles prefabricados 24.5
Dias de trabajo 2170
TENDIDO DE LADRILLO
Hormigon 85
Acero 28.5
Ladrillos 60
Paneles prefabricados 25.8
Dias de trabajo 1040
TENDIDO DE ACERO
Acero 56.5
Dias de trabajo 440
INTERIORES
Tablones 20.5
Acero 38.5
Componentes mecanicos 14.3
Componentes electronicos 12.8
Dias de trabajo 782
TORRES DE REFRIGERACION
PREPARATORIOS
Grava 92
Asfalto 98
Hormigon 85
Dias de trabajo 920
TENDIDO DE ACERO
Acero 38.8
Componentes mecanicos 6.7
Componentes electronicos 0.8
Dias de trabajo 782
TENDIDO DE ACERO
Hormigon 68
Acero 30.5
Dias de trabajo 948
Revisions:
Old revisions of this mod are available below. Click the link to download.